Activity 3
From FollowTheScore
| Activity Summary | |
|---|---|
| Release State: | 3 - SOW Ready |
| Phase: | Sequence: |
| Project Management | 1 |
| Practice: | Type: |
| (Cross-Practice) | Project Management |
| Discipline:
(Not Applicable) | |
SUMMARY
Identify, Build and Manage Customer Team Members
LEVEL OF EFFORT TABLE
The following table outlines the level of effort by role:
| Role | Est. Effort (days) | Role | Est. Effort (days) |
|---|---|---|---|
| Senior Project Manager (L5) | 1 | Senior Consultant (L4) | 0 |
| Principal Consultant (L5) | 3 | Consultant (L3) | 0 |
| Solutions Architect (L5) | 0 | Remote Engineering (L2) | 1 |
| Project Manager (L4) | 0 | Associate Consultant (L1) | 0 |